UTILITY HIGH LOAD FACTOR INCENTIVES

In many states utility compaies offer incentives for new customers or expanding customers that have a high load factor profile.

Below are examples of those rates:

AL Alabama Power Transmission or distribution Primary customer =>3,000 KW 90% Load Factor negotiable rate =>27,000 KW 10-year term.
AR Entergy Commercial and industrial =>2,500 KW 80% load factor 75% power factor 5-year term.
FL Florida Power & Light Customers =>20 KW demand 1-year term reduced KW and kWh charges.
GA Georgia Power Reduction on KW and kWh charges negotiated term.
IA Alliant Energy Transmission customers only 50% discount 1-year minimum term.
IA Alliant Energy - Interstate Power & Light Primary customer 2.5% and $0.22 per KW demand reduction.
IN Duke Energy Customer adjacent to transmission or distribution lines taking primary service =>25KW.
IN Nipsco Facilities adjacent to existing infrastructure, contract =>10,000 KW 5-year term.
KA Westar Energy NOTE: HLF now LGS Reduced service charge and reduction on KW and kWh charges negotiated term.
LA Entergy Customers taking service from 115,000V Transmission Line or Greater reduced KW and kWh charges.
LA SLECA Must have =>60% load factor =>1,000 KW Reduced KW and kWh charges negotiated term.
MD Potomac Edison - First Energy Freeze base distribution rates through May 31, 2019 Ohio communities, colleges and universities, small businesses or low-income customers 3-year term.
MN Alliant Power - Interstate Power & Light Transmission customers only 50% discount 1-year minimum term.
MS Entergy KW Demand and kWh reduction =>1,000 KW 5-year term minimum.
NY NYSEG & RG&E Commercial and industrial customers =>500 KW 90% load and power factors reduced KW and kWh charges.
OH American Electric Power (AEP) Customers =>100 KW 1-year term minimum =>1,000 KW 2-year term minimum contact reduced KW and kWh charges.
OH Ohio Edsion  - First Energy Ohio only businesses with => 30 facilities majority refrigeration load =>1.5M kWh annually, load factor =<70% expires May 31, 2024. 5-Year Term.
OH The Illuminating Company -First Energy Ohio only businesses with => 30 facilities majority refrigeration load =>1.5M kWh annually, load factor =<70% expires May 31, 2024. 5-Year Term.
OH Toledo Edison - First Energy Ohio only businesses with => 30 facilities majority refrigeration load =>1.5M kWh annually, load factor =<70% expires May 31, 2024. 5-Year Term.
SC SANTEE Commercial and industrial =>60% load factor reduced KW and kWh charges negotiated term.
VA A&N Cooperative Reduced KW and kWh charges 5-year term 60% load factor 80% power factor.
WI Madison Gas & Electric Commercial and industrial =>1,000 kW 60% load factor reduced KW and kWh charges.
WI Alliant Energy Primary customer 2.5% and $0.22 per KW demand reduced charges.

See other Utility Economic Development Incentives